Oslo The City of Oslo has established a goal of 50 % reduction in greenhouse gas emissions by 2030, and to be carbon neutral by 2050.
PHAC system
To use the electricity when it’s available AND locally/off grid (PV-panels), to reduce the amount of electricity needed (run the heatpump only for cooling) and last-but-not-least to reduce the load on the electricity grid.
Gardencity Lichterfelde
The project covers the energetic modernization and refurbishment of a 1930's building ensemble with 316 old and 50 new apartments in the south of Berlin, Germany. The project is based on the usage, storage and management of regenerative energy earnings with the aim of a very moderate, socially
A smart HP for large diffusion
Whittlebury Hall Hotel & Spa offers a wide range of modern corporate hospitality facilities for conferences, exhibitions and training as well as extensive leisure and dining facilities. A smart, safe and easy installation heat pump that covers the heating and cooling needs for each room
Rotterdam
Rotterdam With the construction of the Maastoren, the Rotterdam skyline gained a new icon. Erected in the Kop van Zuid area, the Maastoren has a height of 165 m, making it the tallest building in the Netherlands.
Название проекта
The chapel in honor of the Holy Martyrs Vera, Nadezhda, Lubov and their mother Sophia is in the village of Red Barricades, the Astrakhan Region. The objective of this project was to create the controlled climate in the chapel with stable temperatures throughout the year (heating and cooling
Bakkavor
The R717 heat pump with combined cooling & heating mode has replaced the traditional chiller plus (gas) boiler system.Now each year more than 800 tons CO2 are saved (57 % emission reduction). Egnineers of Bakkavor have identified the need of: - 760 kW heating capacity via 45 m³
Zero Energy Homes Arnhem
In Arnhem 96 homes have been renovated to Zero Energy level by adding a new outer shell including insulation, replacing the windows and completely replacing all technical installations by our Nathan Energy Module.
Terracity Mall
The 12,000 kw/h capacity required by the shopping center for cooling and heating is provided by HP units using underground water. The complete building is cooled and heated by HP units ; 700 Climate Master water to air HP units, 2 Clivet water to water HP chillers, 11 Lennox water to air rooftop